La Rambla Makeover Costs Rise by €5.73 Million Before February Opening
Barcelona is approving a €5.73 million cost increase for the La Rambla works. See what the extra money pays for and how the budget has grown since work began.

The Ajuntament de Barcelona (Barcelona City Council) is approving a modified plan for the La Rambla renovation that adds €5.73 million to two of its construction contracts, La Vanguardia reported. The vote comes about three months before the works are due to finish.
Most municipal groups are expected to back the change, so the extra spending should go through. The change modifies the redevelopment project itself, because two works contracts now cost more than first agreed. The PP (People’s Party) group has said it will vote against it, so the result will not be unanimous.
Where the extra €5.73 million goes
The city gives four reasons for the overrun. In its own wording, they cover support work for archaeological interventions, extra security for the public space, rehabilitation of the sewer network, and the conservation and improvement of existing features along the promenade.
The vote takes place at the so-called comisión escoba (“broom committee”), a session that bundles proposals from the government and the opposition that would normally be split across four separate council committees.
A faster timetable and a growing bill
Work on La Rambla runs at full speed, weekends included. The city wants it finished for an opening celebration on Feb. 13 and 14. That date falls three months ahead of the municipal elections on May 23, 2027.
Mayor Jaume Collboni, a Socialist, halved the schedule for the project. It was first planned to last close to six years. According to La Vanguardia, shop owners and residents on La Rambla and nearby streets welcomed the shorter timetable. The paper also says the faster pace has made an already complicated job on one of the city’s busiest streets harder still.
When work began, the renovation was estimated at about €40 million. The council’s official website now lists a much higher updated budget. Steep increases in the price of building materials are among the reasons the figure went up. Last year the Diputació de Barcelona (the provincial government) gave the city €21 million to help pay for the project.
What it means for residents and visitors
For people who live near La Rambla or cross it every day, the vote changes how much the project costs, not when it ends. The target remains the February opening, and crews are expected to keep working through weekends until then.
The final price of the renovation will only be known once the works are fully complete. Large public projects rarely avoid cost overruns, La Vanguardia noted, and this one has already grown well beyond its starting estimate.
What happens next
Once the committee approves the modified project, the contractors continue under the revised budget. The next fixed date is the opening celebration on Feb. 13 and 14, followed by the municipal elections on May 23, 2027.
Source: La Vanguardia