Repsol Sues Power Firms for €120 Million Over April 2025 Blackout
Repsol has sued Iberdrola, Naturgy, Endesa and Red Eléctrica for about €120 million over the April 2025 blackout, including losses at its Tarragona site.

Repsol is taking three Spanish electricity distributors and the national grid operator to court over the blackout of April 2025, seeking around €120 million for losses at five of its industrial complexes, including Tarragona. The oil and chemicals group says the outage forced those plants out of normal operation.
A company spokesperson confirmed on Monday that claims had been filed against Iberdrola, Naturgy, Endesa and Red Eléctrica de España (REE, the company that runs Spain’s high-voltage grid), but would not confirm the figure. El Confidencial first reported the €120 million amount, and RTVE also reported it, according to Spain in English. Iberdrola, Naturgy, Endesa and Redeia, the parent company of REE, declined to comment.
Who Repsol is suing, and where
The claims cover complexes in A Coruña, Bilbao, Cartagena (Murcia), Tarragona and Puertollano (Ciudad Real). When the power went, the refineries switched to emergency mode at much lower output. That cost production and damaged equipment, the company says.
Each claim targets the local distributor plus REE, because Spain’s distribution networks are split by territory. Naturgy supplies the A Coruña site. Iberdrola supplies the Petronor refinery in Bilbao and the Cartagena complex. Endesa, which belongs to Italy’s Enel group, supplies Tarragona and Puertollano. Repsol wants the distributor and REE in each case held jointly and severally liable, a legal term meaning each can be made to pay the full amount.
The company filed the suits in October 2026, after formal demands and attempts at an out-of-court deal went nowhere. At a results presentation on April 30, 2026, chief executive Josu Jon Imaz said the company had approved legal action. He had earlier promised to get back “every last euro lost.”
How the figure has changed
Repsol’s first estimate of its total losses was up to €175 million, and it later said it would claim €125 million. The reported €120 million covers only damage from the April 28 blackout itself. Separate outages at Cartagena and Puertollano in the days before and after are not part of the case.
Repsol is not the only energy group seeking money. Moeve has filed its own claim of around €50 million, which takes the total sought by the two companies to roughly €170 million.
What it means for Catalonia and Spain
The lawsuit brings the blackout’s cost into the courts, with Tarragona’s petrochemical complex among the sites at stake. On April 28, 2025, much of Spain and Portugal lost power, some areas for as long as 16 hours. Several investigations have pointed to a voltage surge as the cause, and the CNMC (Spain’s markets and competition regulator) has opened its own investigations involving large energy companies.
Estimates of the wider damage vary widely. Spain’s Economy Ministry now puts the net cost to the economy at around €415 million, revised down from an early estimate of up to €800 million. CaixaBank Research put the net hit at under €400 million, finding that shoppers caught up on postponed spending in the following days. The national employers’ association estimated direct business losses at around €1.6 billion, counting closures at factories, shops, bars and restaurants, and the self-employed workers’ association ATA put losses among its members at around €1.3 billion.
Energy-hungry factories and petrochemical plants took much of the physical damage, since their equipment stopped without warning.