Neighbors Take UB’s Two New Diagonal Buildings to Court
Residents of the University Zone are challenging in court the UB's plan for a new Mathematics faculty and an IBEC building on the Diagonal, a €71.5 million project.

A residents’ association and five property communities in Barcelona’s University Zone have taken the city’s urban plan for two new university buildings on the Diagonal to court, according to Ara. The plan would let the Universitat de Barcelona (UB) build a new Faculty of Mathematics and Computer Science next to the Faculty of Economics. The UB and the Generalitat (Catalan government) are going ahead anyway, and a ruling for the neighbors could in theory force demolition of buildings that do not comply with the plan.
The Ajuntament de Barcelona (city council) plenary session definitively approved the special urban planning project in September 2024. The neighbors went to court after none of their objections were accepted during the planning process.
What the neighbors argue
The residents say a change of this kind could not be made through a special plan and required a modification of the Pla General Metropolità (Metropolitan General Plan). In their view the land zoning is being changed without the necessary authorization.
They also say the buildable ceiling rises disproportionately. The plan places a 14,000 square meter building on a plot that could reach 47 meters in height. A building above ten floors, they argue, is unsuitable and could leave much of the neighborhood in shadow during the day. “We believe there is an abuse of buildability,” they told Ara.
Other complaints cover parking and heritage. No new parking is planned, although more students and staff would come to an area they describe as already strained. The Pedralbes Gardens sit right next door. In the coming days the neighbors will file a formal document with the Department of Culture, asking it to act in defense of the Pedralbes Palace, a property cataloged as national heritage that they say would suffer a visual impact.
The residents say they are not against the new faculty. They want it better integrated into an area already heavily shaped by university activity, surrounded as they are by campuses and the Bruc barracks.
What the UB and the city say
UB sources did not discuss the specifics of the appeal but said they do not share “the anxiety of this neighborhood group”. They noted that the area has been mainly university land for more than 70 years and said that activity benefits it. They described the Faculty of Mathematics and Computer Science as one of the Catalan university system’s faculties with the most potential, with the highest cut-off grades.
The city council says the plans followed the required procedures and that their legality and compliance with reports from sectoral bodies were checked. Municipal sources add that the plan had majority backing in the plenary. In September 2024 it passed with votes from the PSC, Junts, Barcelona en Comú, ERC and Vox, while the PP abstained. The PP, Junts and the commons also asked the municipal government to talk with the neighbors.
Why it matters: timing and risk
The plan covers two buildings, one on each side of the Diagonal: the Faculty of Mathematics and the headquarters of the Institute for Bioengineering of Catalonia (IBEC). The investment is 71.5 million euros. Works are forecast to start at the end of 2027 and run until 2029.
The court calendar is less clear. If the case ends in the neighbors’ favor, Ara reports, the ruling could even force demolition of constructions built out of order. Residents and commuters in the area can watch for the Department of Culture filing and any court dates, none of which have been announced.
Source: Ara