Barcelona Council Lifts Demolition Threat on 672 Homes in Sants
Barcelona's city council gave provisional approval to a plan that spares 672 homes in Sants from demolition and rules out tearing down Can Vies.

Residents of 672 homes in Barcelona’s Sants district no longer face demolition plans that have hung over their buildings, in some cases for decades. The full council of the Ajuntament de Barcelona (city council) gave provisional approval on Friday, Nov. 27, to a change in the metropolitan general plan (MPGM) that removes the demolition designation from 602 flats on Rambla Badal and 70 around the Sants cutting (the “calaix de Sants”), according to the newspaper Ara.
One step remains: the Generalitat (Catalan government) must give its approval through the Barcelona Urban Planning Subcommittee. The plans that put the buildings at risk had long been outdated.
How the council voted
PSC, Barcelona en Comú, ERC and Vox voted in favor. The PP abstained and Junts voted against.
What changes on Rambla Badal
On Rambla Badal, 43 buildings with 602 homes are released from the demolition designation. Number 188 does not meet the planning criteria to be included in the change, so it stays outside the MPGM. The city government has nonetheless agreed with Barcelona en Comú to protect it. A report signed by the head of urban planning says the council will neither expropriate nor demolish the building, so the residents of its eight flats can stay. At number 121, which the city owns, its homes will become protected housing.
What changes around the Sants cutting
Here the council is revising a 2003 plan and drawing a new layout for the part that was never carried out. It affects Carrer de Burgos, Riera de Tena, Bonaventura Pollés, Jocs Florals and the Can Vies building. The deal here rested on a promise to speed up a public housing block of 50 homes on the plot at Riera de Tena 46-56. The block will also house 12 families who were relocated from homes hit by the planning.
The government has also agreed to list both areas as a Conservation and Rehabilitation Area (Àrea de Conservació i Rehabilitació), which makes renovating the freed buildings a council priority.
Why it matters: Can Vies stays
The approved plan rules out demolishing Can Vies, a squatted house. A plan to knock it down and turn the site into green space set off one of the biggest crises of the government of then-mayor Xavier Trias in 2014. Its use as a community facility is now protected, though what will go there and who will run it has not been decided.
Raquel Gil, the district councillor for Sants-Montjuïc, said it is too early to talk about that, because neighbors must first be consulted on the facility’s use. She said this is not the Can Vies plan: it is the plan that lifts the threat for 700 families, creates more housing and more land for facilities.
Source: Ara