New Alstom Rodalies Trains Get Safety Approval, Service Due 2027
Alstom's new series 452 Rodalies trains have won Spanish rail safety approval. Here is what is still pending and when passengers can expect them.
The new series 452 trains that Alstom is building for Rodalies (Catalonia’s commuter rail network) have received authorization from the Agencia Estatal de Seguridad Ferroviaria (AESF, Spain’s state rail safety agency). According to El Periódico, the trains have appeared in the European register of authorized vehicles since Nov. 17. Passenger service is expected in the first quarter of 2027, though El Periódico reports the first 16 trains will carry passengers in spring 2027.
Approval does not put the trains on the tracks immediately. Drivers must be trained and certified first, and the Generalitat (Catalan government) and Renfe, the state operator, still have to set a date for the first service.
Nearly two years of testing
La Vanguardia says the process began in January 2025 and took almost two years of tests, changes and improvements. Most tests ran at night on the Maresme line, a narrow window that slowed the calendar. Problems on the rail network this year did not help either, the newspaper adds.
El Periódico reports that incidents at the factory cut planned supply and stretched delivery times. It cites production problems at the Santa Perpètua de Mogoda plant and errors in assembling the bogies, the wheel and suspension systems.
Alstom said in a statement that the authorization completes the evaluation of the train’s design, subsystems and components under European and Spanish rules.
Deliveries and rollout
La Vanguardia reports that Alstom has gathered around ten units ready to leave the plant. The first two went to Renfe’s workshops earlier this month, and more are due in the coming days. Alstom has committed to delivering the first 16 of the 72 trains Renfe bought for Rodalies before the end of the year. El Periódico says Alstom had originally planned to hand over 27 by year-end.
The Generalitat prefers a gradual introduction over putting every available train into service at once, according to La Vanguardia. It points to Stadler trains in Madrid, which all had to be pulled for several days for adjustments in their first week.
Checks still pending
El Periódico, citing public entries in the European register, says two points remain. The pantographs, the roof equipment that draws power from overhead wires, must still be verified for heights above 5.30 meters. For now the trains cannot run with the ERTMS level 1 signaling system. The newspaper says both should be resolved by spring 2027.
The first line the Generalitat wants to use the trains on is the R1, which for almost its whole route has overhead lines and safety systems compatible with the conditions of the current authorization, El Periódico reports.
What it means for passengers
The new trains mix single and double-deck cars. El Periódico says they have 20% more seats than most current Rodalies trains and that the 72 units should provide 36% more seats across the network. The network is already near its capacity limit, so more seats per train matter for passengers. Diari de Tarragona adds that each side of the train has 12 doors and wider vestibules, designed to speed boarding and shorten station stops.
El Periódico reports that President Salvador Illa and Territori consellera Sílvia Paneque have repeatedly named the arrival of these trains as the point when users would start to notice improvements. Paneque called the approval a step toward improving Rodalies and said it brings the new trains closer, with more capacity.
The renewal will allow the 18 most worn-out Rodalies trains to be retired and 54 new ones added, according to El Periódico. For background on lines, tickets and refunds, see our guide to Rodalies trains.
Other trains expected
La Vanguardia says 24 new regional trains from CAF and 14 trains of the 121 series are also expected in the coming months to reinforce lines that run on both international and conventional gauge. El Periódico gives a different figure for CAF, 38 trains for the Regionals fleet. Diari de Tarragona says the series 452 is part of a purchase of 110 trains for Catalonia worth about 1,275 million euros.
Originally the trains were due in 2026. Government calendars now point to the first quarter of 2027, a date former transport minister Óscar Puente described as the most prudent, according to Diari de Tarragona.
Sources: La Vanguardia, El Periódico, Diari de Tarragona