TMB Awards 1.5 Million Euros in Emergency Deals to Fix Metro L2 Track
TMB gave three firms emergency contracts to fix rain-damaged L2 track at Artigues. The La Pau to Gorg cut lasts until Dec. 3 and hits some 25 thousand daily riders.

Barcelona’s metro operator has signed three emergency contracts worth about 1.53 million euros to rebuild a damaged stretch of track on Line 2 (L2) near Artigues, according to the local outlet Metrópoli Abierta. The contracts were awarded without a public tender.
The line has been cut between La Pau and Gorg since Nov. 2, and the closure is due to last until Dec. 3. Until then, trains do not stop at Verneda, Artigues-Sant Adrià or Sant Roc.
Who is doing the work and for how much
TMB (Transports Metropolitans de Barcelona, the city’s bus and metro operator) split the job into three contracts, Metrópoli Abierta reported:
- GEOTRESTEC, S.L. is carrying out injection work under the track for about 0.81 million euros.
- COMSA, S.A.U. is renewing the concrete slab and the track for about 0.68 million euros.
- TPF GETINSA EUROESTUDIOS handles site management and health and safety coordination for a much smaller sum, a little over forty-one thousand euros.
Under the emergency rules, no contract can run longer than six months, and the building contracts are capped at three months.
How heavy rain damaged the track at Artigues
The problem surfaced during a routine visit on Oct. 8. Inspectors found that the track at Artigues had become significantly worse. TMB said heavy rain in the province, especially on Oct. 3, may have caused it.
The inspection turned up water in the track slab and the layers beneath it, cracks and breaks in the slab at several points, and most of the damage around the exit of the crossings, where trains switch tracks.
On Oct. 11, TMB set alarm limits and warnings in case large movements were detected. During the night of Oct. 18 to 19, crews began temporarily anchoring the track to the concrete so trains could keep running at reduced speed.
Why TMB skipped the normal tender
In its justification, TMB called the damage unforeseeable and said it had developed quickly and unexpectedly compared with what was known about the infrastructure. A report cited by Metrópoli Abierta pointed to “a significant deterioration in a short period of time” as the reason to drop ordinary procurement.
The operator also said its stopgap measures, such as speed limits and shoring, cut the risk for a while but did not fix the underlying cause.
Why it matters for L2 riders
TMB chief executive Xavier Flores said on Oct. 29 that the partial closure is a nuisance and that around 25 thousand passengers a day are affected. He added that the tracks are inspected and maintained every night, and that the company acted once a problem was found.
TMB chose to close part of the line because the repair goes faster that way. Keeping full service would have meant working only at night, with trains held to 15 km/h through the damaged section.
What happens next
Dec. 3 is the planned last day of the cut between La Pau and Gorg, a few weeks before Christmas, when ridership on the metro climbs. TMB expects full service on L2 to return at the start of December.