Catalan Engineers Urge Next Government to Fund Rodalies, AP-7 Upkeep
Catalonia's civil engineers want the next government to put maintenance and safety on Rodalies and the AP-7 ahead of big new projects. Their ten-point plan explained.

Catalonia’s civil engineers have asked the next government to spend on maintaining and making safe the infrastructure it already has, rather than on large new projects. The Col·legi d’Enginyers de Camins, Canals i Ports de Catalunya (the professional body for civil engineers) and the foundation Cercle d’Infraestructures drew up a ten-point document, according to La Vanguardia. They are presenting it to political representatives this week.
Two networks stand out for commuters and drivers: the Rodalies commuter rail service and the AP-7 motorway. The document does not mention a third tunnel under Barcelona or the new rail corridors that the Generalitat (Catalan government) and the Spanish Transport Ministry hope to build.
Rodalies: safety first, capacity last
The engineers set a four-step order of priorities for Rodalies trains. First comes safety, covering slopes, cuttings, tunnels, bridges and signalling. Second is the reliability of the service. Third is running the current network at the highest possible capacity. Fourth is adding capacity.
That order leaves out the burying of rail lines and other works that the engineers describe as more urban than railway-related. La Vanguardia notes that the network has suffered years of low investment, and that this was exposed in January after the fatal accident of a trainee driver in Gelida.
High-speed line to Madrid
The same approach is requested for high-speed rail, which, according to La Vanguardia, enters the elections with more than 110 deaths from the Adamuz and Urda accidents. Dean Pere Calvet says there can be no doubt on this and calls for a continuous maintenance plan. He considers works on the Barcelona-Madrid line urgent.
Calvet was one of the strongest opponents of the closure of the line proposed by former minister Óscar Puente. He views favorably the plan of Puente’s successor to carry out the works without halting rail traffic. Of the next government, the engineers ask for a calendar, a budget and an explicit goal of a direct service in under two and a half hours.
AP-7: a funding model for upkeep
On the roads, the engineers point to the AP-7. Truck traffic has grown 80% since tolls were lifted, and no improvements have been carried out since, according to the report as relayed by La Vanguardia. They propose a financing model for maintaining the high-capacity road network to stop its progressive deterioration. Calvet says it should be “stable, sufficient and earmarked,” so that money returns to the same network, and fair between territories.
Pay-per-use is one of the options they consider. Salvador Alemany, former chairman of Abertis, raised it a few weeks ago at the Col·legi’s headquarters. The authors say the system should be chosen in the first year of the term, through work led by the Spanish state with the regions taking part. If that proves impossible, they say the Generalitat should receive the powers needed to introduce the model in Catalonia. Alemany had predicted that approach would be a mistake, arguing the system should be unified across Spain to avoid repeating past errors.
Why it matters
Rodalies delays and the state of the AP-7 affect daily commutes and freight across Catalonia. The paper’s proposals are recommendations, not decisions, and the engineers are asking the future government to commit to spending what has already been budgeted “to bring Catalonia up to date.”
What to watch next
The engineers are meeting political representatives this week. They want the funding model for high-capacity roads defined within the first year of the next term.
Source: La Vanguardia